STACKING PRO-JAX
According to OSHA, all scaffolds must be restrained from tipping. This can be accomplished in one
of three ways:
1. For free standing scaffolds, the maximum platform height must not exceed 3 times* the narrowest
base dimension.
2. Guying the scaffold.
3. Tying the scaffold to a wall or other solid structure.
*Federal OSHA allows a maximum platform height of 4 times the narrowest base dimension. However, Bil-Jax recommends
that the maximum height be limited to 3 times the narrowest base dimension on all Pro-Jax utility scaffolds.
When additional platform height is required on a free standing scaffold, outriggers may be used to
extend the base dimensions. Bil-Jax has different size outriggers available for use with Pro-Jax
units. 18" wide outriggers are for use with two-frame high scaffolds and 24" wide outriggers are for
use with three-frame high scaffolds.
Whenever Pro-Jax units are stacked, outriggers are required! Do not use a
Pro-Jax utility scaffold over 1 frame high without outriggers. Failure to use
outriggers will make scaffold more likely to tip over causing serious injury
or death!!

BUILDING A TWO FRAME HIGH SCAFFOLD

If the platform height needed is between 6' and 11' 6", it will be necessary to install 18" wide
outriggers and a second scaffold level prior to use.
STEP ONE
Erect the base
unit (one frame high scaffold) by
following the previous instruction.
STEP THREE
Tighten clamp securely. Clamp must be flush against scaffold leg and casters must be
in contact with the surface.
Top View
Outrigger
Frame
STEP FOUR
Add
second scaffold level by
stacking end frame over
insert pins in top of base
unit end frames. Secure
in place with snap pins.
®
UNITS FOR ADDITIONAL HEIGHT
WARNING
STEP TWO
four (4) outriggers and secure with snap pin
provided with each caster. Set caster brake.
Clamp outrigger to end frame at a 90
Tighten
Securely
Outrigger
Install casters into all
°
angle to the side brace.
Side View
Frame
Leg
STEP FIVE
side braces (minimum two),
platform, and guard railing at
desired height per the previous
instructions (Building a One
Frame High Scaffold).