Anderson ANM75 Kullanım Kılavuzu - Sayfa 9
Brülör Anderson ANM75 için çevrimiçi göz atın veya pdf Kullanım Kılavuzu indirin. Anderson ANM75 18 sayfaları.
3. Profile Plate Adjust
Provide an opening in the duct 80mm larger than the external burner dimensions
gap on all 4 sides.
Profile plates are not required for good burner operation, but uniform velocity must
be maintained for the full length of the burner. If velocity is not uniform, profile
plates can be used to correct this condition. Profile plates should be positioned
flush with the firing end of the burner. If necessary, the plates can be located up to
1/2" back from the firing end, but under no circumstances should they be in front
of the burner.
4. Valve train connection
Locate the valve train as close as possible to the burner to make sure gas reach the
burner during the trial for ignition time. Sufficiently size shut off valves in the valve
train. In order to decrease pressure loss in pipe, minimize piping elbows to be used
while pipe union is recommended. Flexible pipe is good optional but pressure lost
must be considered.
5. Flame monitoring
There are two different types of flame sensors:
UV scanners
Each ANM75 Series burner is capable of U.V. flame monitoring. The burner will not
come equipped with a UV scanner. A ½" BSPT connection is provided on each
burner for the connection of UV scanner.
Flame Rod
If the flame rod option was selected when the burner was ordered, the burner will
be delivered with the flame rod already installed on the burner.
10.6 Checklist after installation
To verify the system was properly installed, perform the following checks:
– Be sure there are no leaks on gas lines.
– Be sure all the components for flame monitoring, pressure switch and wiring are
properly installed.
– Be sure all components of the spark ignition system are installed and functioning
properly.
– Be sure the blower rotates in the proper direction. If the rotation is incorrect, have
a qualified electrician rewire the blower to rotate in the proper direction.
– Be sure all valves are installed in the proper location and correctly oriented
relative to the flow direction.
10.7 Prepare for adjustment
After installation of the burner system components is complete, the following steps
should be followed in order to prepare for adjustment:
– Set the air flow switch so that it drops out at 50% below the maximum pressure of
the combustion air blower.
Anderson Thermal Soluions(Suzhou)Co. ,Ltd.
Anderson Thermal Solutions – ANM75 Burner Operation Manual
7