GENERAL OPERATIONS
ROLLER OVERVIEW & REPLACEMENT
The rollers used are the result of extensive research and development and feature a specialized, abrasion resistant rubber of optimal durometer hardness, best suited to the hemp and cannabis
industries. While exhaustive research has shown this material to be the least wearing (while still giving excellent grip and performance), it is not indestructible, and just like the rubber tires on your car,
will not last forever. Because of this, we cannot offer a warranty on our rollers. Roller replacement is an extensive task, but not one beyond most mechanics in the field. The following steps should guide
you on proper roller replacement procedures.
STEPS TO REPLACE THE ROLLER
1. Lock out the main power switch and unplug the machine from the power source. (Figure 1)
2. Remove all the chutes, guards and safety panels necessary to gain full access to the rollers, bearing blocks
and drive chains.
3. Slacken the chain adjuster sprocket and remove the roller sprockets from the roller shafts. It will be
necessary to loosen the two X/X set screws from each sprocket before removing the sprockets from the
roller shafts. The chains can then be removed from the machine to give full access to the bearing blocks
(see Figures 3 and 4)
4. Remove the 8 X/X sized hex head securing screws from each roller coupler before removing the coupler
halves from the roller shafts. Each coupler unit has two keys to couple it to the roller shaft, which must be
retained for reassembly.
5. The top rollers can now be removed by removing the four bearing block securing bolts and nuts, and then
lifting the rollers free from the machine. It is advisable to have help with this operation, as the rollers are
very heavy and two or more people are needed to safely remove and replace them.
6. With all the top rollers free, the lower rollers are removed in the same manner.
7. After removing the rollers from the machine, the two X/X set screws securing each bearing block to the roller
shaft can be loosened and the bearings removed from the shafts.
8. Slide bearings over roller shafts with the collar facing inward. Do not tighten the securing set screws at
this time.
9. Install the lower roller first, being sure to center each one between the bearing blocks. The bolts and nuts
securing the bearing blocks should be only tightened enough to take up the slack at this point.
10. With all the lower rollers positioned in place. The shaft alignment should be checked by using a long straight
edge or string pulled against the top or bottom of the rollers. If the roller shafts are not aligned, adjustment
can be made by raising or lowering each bearing block as needed. A x/x hex head adjustment screw is
located under each lower roller bearing block to make this adjustment very precise. (see Figure 5)
FIGURE 3
CHAIN ADJUSTER
SPROCKET (TENSIONER)
UPPER
ROLLER
SPROCKET
LOWER
ROLLER
SPROCKET
FIGURE 6:
TIGHTEN BEARING COLLAR
SET-SCREWS ONLY AFTER
MAKING SURE ROLLERS
ARE CENTERED BETWEEN
BEARING BLOCKS.
For more information or to watch our DIY video tutorials visit cprosolutions.com
11. With roller shafts aligned and each roller centered between the bearing blocks, tighten the bearing block
nuts completely, so as not to come un-tight in use.
12. Tighten the bearing collar set screws at this time. (see Figure 6)
13. Attach the top rollers, again leaving the bearing block bolts and nuts just tight enough to eliminate
sloppiness, but with freedom of moment vertically.
14. Carefully roll an xxx" thick shim (easily made from card stock or layers of paper) in-between the top and
bottom rollers on each end simultaneously and tighten the bearing block securing nuts and bolts fully.
This allows for very slight running clearance and free movement of the upper and lower rollers for ease of
assembly when installing the drive chain.
15. The roller shaft coupler can now be installed between each roller set. Be sure to center and install the keys
in the keyways before tightening the 8 hex head screws evenly.
16. Reinstall the chain to the motor sprocket before installing the roller drive sprockets.
17. Install each roller drive sprocket into the chain as you install them on their respective shafts.
18. The roller drive sprockets must align with the adjuster sprocket, so as to keep the chain from being pulled
sideways, bending or kinking. (see Figure 7)
19. The xx" key must be installed in each roller drive sprocket and set flush with the face of the sprocket,
before the drive sprocket securing set-screws are tightened.
20. The drive chain must now be tensioned via the adjuster sprocket to give only minor slack when the long
side is deflected.
21. Once the correct tension is achieved, secure the adjuster sprocket by fully tightening the xx/" bolt and nut.
22. Replace all guards, chutes and safety panels before testing or operating unit.
FIGURE 4
SET SCREWS
(2 EACH)
CHAIN MUST BE IN-LINE WITH ADJUSTER
BEARING COLLAR
SET-SCREWS
SPROCKET WHEN SET-SCREWS ARE
MAKE SURE ROLLER SPROCKET KEY IS
CENTERED INSIDE ROLLER SPROCKET
BEFORE TIGHTENING SET-SCREWS.
LOWER
ROLLER
ROLLER HEIGHT
ADJUSTMENT
SET-SCREW
ROLLER SHAFT
SPROCKET
UPPER ROLLER BEARING
BLOCK SECURING BOLTS
ROLLER
SHAFT
LOWER ROLLER BEARING
BLOCK SECURING BOLTS
SPROCKET KEY
FIGURE 7:
TIGHTENED TO ROLLER SHAFTS.
OWNERS MANUAL
XL MEGABUCKER
FIGURE 5
GREASE (ZERK) FITTINGS
(0NE PER BLOCK)
UPPER ROLLER
ROLLER SHAFT
COUPLERS
LOWER
ROLLER
LOWER ROLLER HEIGHT
ADJUSTMENT SCREWS
ROLLER SHAFT
SPROCKET
ROLLER SHAFT
SET-SCREW
CHAIN ALIGNED
(STRAIGHT)